Open for business! Driving around downtown Clemson just got a lot easier. Thanks to the recent patch of clear weather, and the joint efforts of Clemson University, our contractors, and the City of Clemson, the sections of construction along Highway 93 that were scheduled during Spring Break are now open – 10 days ahead of schedule! University Facilities appreciates the collaboration that resulted in the quick completion of work and thanks the Clemson Community for its patience.
Hillcrest Avenue, College Avenue and Sherman Street are now fully accessible to traffic.
Access to and from Hillcrest Avenue at Highway 93 will be closed from March 16 – 26 to allow workers to install underground utilities in the area.
The contractor, A. West, said lower traffic volumes during Spring Break will allow them to focus their efforts on this project and other areas along Hwy. 93. See the visual below for closure and alternate route information.
Beginning at 3 p.m. March 15, A. West Construction will begin placing barricades along Highway 93 to prepare for the installation of a new electrical duct bank at the intersection of College Avenue and Highway 93. The contractor will place the final barricade at 5 p.m., which will prevent vehicles from entering Highway 93 from College Ave. Downtown Clemson will be completely accessible to travelers entering northbound College Ave. from Highway 93. A notable exception are CATbuses that run downtown, which workers with construction flags will direct from southbound College Ave. onto eastbound Highway 93 during this closure.
The intersection is scheduled to reopen April 2, barring any inclement weather conditions, which may delay the reopening. Officials will reassess the construction timeline on March 13. If the forecast allows this section to be completed on schedule, there will only be one remaining closure of the intersection at the end of the project for the final paving of Highway 93.
Sherman Drive
Duct bank construction will also occur during this time on Sherman Drive, however, two-way traffic will be maintained. Traveler access between Sherman and Highway 93 will be unaffected. Officials expect the work to be completed by April 3.
The construction plan above details traffic control during the project.