Manhole construction at the intersection of Highway 93 and College Avenue is scheduled for Dec. 27 through Jan. 7. What you need to know Drivers approaching the intersection traveling westbound on Highway 93 South will be able to turn right onto College Avenue, as well as continue through the intersection along Hwy. 93. Vehicles approaching […]
Update: This project has been postponed and will be rescheduled for some time after December 20th. Starting December 15, traffic heading westbound along Highway 93 will be required to turn right onto College Avenue to allow for construction of a new electrical manhole at this intersection. Traffic entering 93 from College Ave. will only be […]
Update: This project has been postponed and will be rescheduled for some time after December 20th. In the next phase of Highway 93 construction, workers will install a new electrical manhole at the intersection of Highway 93 and Williamson Road. Construction will take place from Dec. 11 through Dec. 14 and will require the limitation of traffic […]
From Monday, December 3 until Friday, December 14, Highway 93 will be reduced to one-lane from College Avenue to Williamson Road. Traffic shifts will occur at Hillcrest Drive and Church of Christ driveway, with barricades leading drivers from the northernmost lane to the southernmost and back again. Entrances to driveways as indicated in the visual […]
Beginning Nov. 4, S.C. Highway 93 on Clemson’s main campus will be reduced to one lane from College Avenue to Williamson Road. Only westbound traffic toward Williamson will be allowed to travel through this area. The Mell Hall parking lot will be inaccessible during Fall Break on Monday and Tuesday, and will reopen on Wednesday […]
As utility work continues on S.C. Highway 93 (Hwy. 93) on Clemson’s main campus, drivers should expect delays. During October, there will be intermittent two-lane closures from Centennial Blvd. to College Ave. as workers install manholes in the road. Also in that timeframe, workers will close two lanes on Hwy. 93 from Centennial Blvd. to […]
Barring additional weather delays, Highway 93 is expected to be open on Monday, August 13. The intersection of Highway 93 and College Avenue will completely close on Wednesday, July 25 and reopen on August 10. Two-lane, two-way traffic along 93 between Cherry Street and Sherman Street will reopen at this time. The date for this […]
Highway 93 from Cherry Road to Sherman Street will close completely on Saturday, July 14 at 5 am. This section of 93 will remain closed until July 22nd. A one lane road will remain open between Sherman Street and College Avenue during this time. Flaggers will be present 24 hours a day to allow access […]
A significant section of Highway 93 will be closed to traffic on Thursday, July 5, from 9:00 PM until 6:00 AM the following day. The closure will span from the intersection with Sherman Street to the intersection with Cherry Road. The closure is necessary in order to tie new chill water lines from 93 to […]
Due to the difficulties and safety concerns that arose on Sunday, June 24 with attempting to prep barricades and fencing in advance of closing additional street access, the next barricade extension will take place on Sunday, July 1 while traffic is lightest. The road construction traffic barriers will be extended through the College Avenue intersection. Once […]